Bickerton Road, Malpas – Culvert reconstruction

Due to ongoing structural deterioration, the south end of Mossmere culvert has collapsed.

Temporary two-way traffic signals are currently in place and will remain until reconstruction of the culvert begins. For your safety and the safety of others, please do not move or tamper with the signals.

What is happening

We will begin reconstruction of the collapsed section of the culvert on 15 August 2025, with works expected to last approximately seven weeks.

As part of the scheme, we’ll be undertaking the following works:

  • Clearing vegetation from the surrounding area
  • Installing access scaffolding
  • Removing the collapsed section of the culvert
  • Constructing new foundations
  • Rebuilding the brick arch and headwall
  • Installing a new parapet
  • Desilting the watercourse
  • Completing minor resurfacing works

Under current Health and Safety legislation and for the safety of our workforce and members of the public, it is necessary for a road closure to be in place for the duration of the scheme.

Diversion Route

There is a signed diversion in place and members of the travelling public, including cyclists are advised to follow this. See the full diversion route.

Further information

  • Emergency access will not be maintained.
  • Emergency services are aware of the closure and the diversion arrangements are in place for emergency vehicles.
  • The road closure is necessary to protect the safety of both members of the public and our workforce
  • Diversion routes are in place and signed
  • Local businesses will remain open and access will be facilitated where possible via diversion routes
  • Delays are expected and motorists should plan journeys
  • Access will not be maintained for pedestrians and cyclists.

Mossmere culvert collapse

Mossmere culvert collapse view from the carriageway

Mossmere culvert