Brook Street, Macclesfield – Highway improvements
We are are carrying out highway improvement works along Brook Street, Macclesfield from 10 February 2023. The work will take place between the junction with Sunderland Street to the junction with Leigh Street and will include resurfacing, traffic signal upgrades and new road markings.
Resurfacing works will also take place on Sunderland Street from the junction with Park Green to Townley Street from 20 February.
To minimize future visits and closures, whilst we’re here we will also be undertaking maintenance activities such as sign cleansing and sign reductions, replacement of pedestrian the guard rail and renewal of uncontrolled pedestrian crossings.
We understand there is no right time to undertake this work and the scheme has been carefully planned to minimise disruption to local residents, businesses and members of the travelling public.
When and what is happening
Works to deliver the improvements will start on Friday 10 February 2023 and will be complete by mid March. The works will take place under phases as detailed below and will include road closures:
Brook Street
Phase 1 – Carriageway resurfacing and traffic signals upgrade
Brook Street – Sunderland Street to A523 The Silk Road
10 February to 19 February 2023
24 hour road closure
Phase 2 - Carriageway resurfacing
Brook Street – A523 The Silk Road to Leigh Street
18 February to 19 February 2023
Road closure between 08:00 – 17:00
A523 Silk Road – Mill Lane to A537 Buxton Road
18 February to 19 February 2023
Road closure between 08:00 – 17:00
Phase 3 – Footway resurfacing
Brook Street – Sunderland Street to A523 The Silk Road
20 February to 26 February 2023
24 hour Eastbound road closure
Phase 4 – Footway resurfacing
Brook Street – Sunderland Street to A523 The Silk Road
27 February to 06 February 2023
24 hour westbound road closure
Phase 5 – Carriageway resurfacing
Brook Street - Sunderland Street to A523 Silk Road
07 March to 10 March 2023
08:00 – 17:00 road closure
2-way temporary traffic signals will also be in place at the junction with Sunderland Street during this time
Phase 6 – Carriageway resurfacing
Sunderland Street – Park Green to Townley Street
10 March to 11 March 2023
Road closure between 09:30 – 15:30
Diversion Route
There is a signed diversion in place and members of the travelling public are advised to follow this, including cyclists due to the nature of the works. Alternatively, a breakdown of the full diversion route can be found here: one.network
Further information
- Those who are directly impacted by these works have been informed by letter
- Emergency vehicle access is being facilitated through the closure
- The road closure is necessary to protect the safety of both members of the public and our workforce
- Diversion routes are in place and signed and should be followed
- Local businesses remain open and access will be facilitated where possible via diversion routes
- Delays are expected and motorists should plan journeys accordingly
- Please ensure that no vehicles are parked along the road